Work Profile Report [12W537]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई-फाईल सं0 22351 लोक निर्माण अनुभाग-2 देहरादून दिनांक 15.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
546.75
Resanction Cost :
546.75
Tentative Cost :
546.75
Exp. Upto Last Fy :
185.38
For CFY 2025-2026
Remaining :
361.37
Demand :
361.37
Allotment :
150.00
Exp in CFY :
0.00
Total Up to Date Exp :
185.38
Construction Started
Sanction on : 1 year 4 months ago
15 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
27 %
Up to Date :
31 %
Tentative Completion date on : 3 weeks 5 days from now
13 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
LHS abutment में 7th lift की concreting का कार्य पूर्ण। 8th lift की reinforcement का प्रगति पर है। -- as on 30-Apr-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: bhowali bridge