Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 30.8 | 30.8 | 0.000 | 30.8 | 15.000 | 0.000 |
12W547 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 256/।।। (3) / 2024 -01 (सी0आर0आई0एफ0) 2022 लोक निर्माण अनुभाग-3 देहरादून दिनांक 29.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1700.00
Resanction Cost :
1700.00
Tentative Cost :
1700.00
Exp. Upto Last Fy : 102.00
For CFY 2024-2025
Remaining : 1,598.00
Demand : 1,000.00
Allotment : 400.00
Exp in CFY : 378.82
Total Up to Date Exp : 480.82
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 28-Jun-2024
Physical Peramenters