Work Profile Report [130W2]

strengthening work from chainage km 200.00 to km 232.00 on NH 119 ( new 534) under NH (O) in the state of uttarakhand on EPC mode
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : job no. 119 (534)-UR-2020-2021-574)

TS Amount (lakhs) : 8232.03 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

8232.03

Resanction Cost :

8232.03

Tentative Cost :

8232.03

Exp. Upto Last Fy :

5,414.20

For CFY 2025-2026

Remaining :

2,817.83

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

5,414.20

Work completed

Sanction on : 4 years 6 months ago

17 Jun 2021

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 8 months ago

30 Apr 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
32
32
32
-
Bridge
3 (50m)
3 (50m)
3 (50m)
-
Jobs
9
9
9
-

Remark

view all

EOT proposal sent to SE 10th Circle NH PWD Dehradun office vide letter no. 1864 / 2C Dated 12-12-2025. The EOT proposal forwarded to the office of Chief Engineer, NH PWD Uttarakhand vide letter no. 4881/27 Yata (40)-Ra.Ma.-10/2025 Dated 15-12-2025.EOT proposal sent to RO MoRTH office Dehradun vide CE NH PWD letter no. 5899 / 43 Ra.Ma. -(U)/2023 Srinagar Dated 17-12-2025. -- as on 31-Dec-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck