Work Profile Report [130W4]
Forest
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : NH-58 UR -2016 -17-476
TS Amount (lakhs) : 20034 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
20034.00
Resanction Cost :
25355.00
Tentative Cost :
25355.00
Exp. Upto Last Fy :
23,392.78
For CFY 2025-2026
Remaining :
1,962.22
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
23,392.78
In Maintenance After Completion
Sanction on : 8 years 7 months ago
16 Sep 2016
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 7 months ago
26 Sep 2021
Actual Completion Date : 3 years 3 weeks ago
02 Apr 2022
Physical Linear Components
Remark
Overall Excess requirement 5321 has been counted as tentative cost increased from 20034 to 25355.00 . -- as on 03-Apr-2025
Assets :
Road ID on IM : Road 1
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: suspension bridge etc gadhera
© PWD Uttarakhand