Work Profile

reconstruction with geometric improvement of existing 2 lane/intermediate lane to 2 lane with paved shoulder configuration from km 300.00 to 338.00 of NH 58 ( length 36.90)


Road ID on IM : Road 1

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: unknown bridge

Administrative Approval Detail : 58-UR-2016-17-474

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 25,734.00 Lacs

Resanction Cost : 25,734.00 Lacs

Exp. Upto Last Fy : 16,877.81 Lacs

For CFY 2024-2025

Remaining : 8,856.19 Lacs

Demand : 0.00 Lacs

Allotment : 0.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 16,877.81 Lacs

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
7 years 10 months ago
29 Aug 2016


Tentative Completion date:
3 years 3 months ago
31 Mar 2021


Actual Completion Date:
2 years 10 months ago
15 Aug 2021


Rating : 100

Remark

Forest Status 00: Not Started

Bottelneck:


100% work is completed -- as on 15-Jul-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 36.9 36.9 36.9 0
No of Bridges 3 3 3 0
Span of Bridges [m] 112 112 112 0
Jobs 1 1 1 0
Currently only Bank Gaurantee information is avilable