Work Profile Report [130W5]

reconstruction with geometric improvement of existing 2 lane/intermediate lane to 2 lane with paved shoulder configuration from km 300.00 to 338.00 of NH 58 ( length 36.90)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest

    Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 58-UR-2016-17-474

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

25734.00

Resanction Cost :

25734.00

Tentative Cost :

25734.00

Exp. Upto Last Fy :

16,877.81

For CFY 2024-2025

Remaining :

8,856.19

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

16,877.81

Sanction on : 8 years 2 months ago

29 Aug 2016

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 3 years 7 months ago

31 Mar 2021

Actual Completion Date : 3 years 3 months ago

15 Aug 2021

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
36.9
36.9
36.9
-
Bridge
3 (112m)
3 (112m)
3 (112m)
-
Jobs
1
1
1
-

Remark

view all

100% work is completed -- as on 15-Jul-2021

Rating : 100

Forest Case Pending At : 00: Not Started

Hindrance / Bottleneck :

Assets :

Road ID on IM : Road 1

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: unknown bridge

© PWD Uttarakhand