Work Profile Report [131W1]

Closed Work वार्षिक योजना 2019-20 के अंतर्गत राष्ट्रीय राजमार्ग संख्या 107(ए ) के किमी 70 से 84.200 के मध्य सुदृढीकरण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : RO/UK/12014/116/Annual Plan/2019-20

TS Amount (lakhs) : 1198 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1198.04

Resanction Cost :

1198.04

Tentative Cost :

1198.04

Exp. Upto Last Fy :

845.84

For CFY 2024-2025

Remaining :

352.20

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

845.84

Construction Started

Sanction on : 4 years 6 months ago

05 Mar 2020

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 2 years 5 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
14.2
14.2
14.2
-

Remark

view all

Work Completed. -- as on 01-Apr-2022

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

© PWD Uttarakhand