Work Profile Report [131W8]
Fin Plan
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : एन0एच0/12014/89/2016/यू0आर0/चारधाम/एन0एच0-2
TS Amount (lakhs) : 41888 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41888.00
Resanction Cost :
41888.00
Tentative Cost :
41888.00
Exp. Upto Last Fy :
25,712.66
For CFY 2024-2025
Remaining :
16,175.34
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
25,712.66
Construction Started
Sanction on : 7 years 8 months ago
20 Mar 2017
Physical Progress:
At start of FY 2024-2025 :
93 %
Up to Date :
94 %
Tentative Completion date on : 10 months 4 weeks ago
30 Dec 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Land Acquisition & Hindrance issues at few locations.
PCOD issued on 15.02.2024
-- as on 04-May-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: SAUDI SERA BRIDGE