Work Profile Report [133W1]
Fin Plan
Remarks
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : SNH 12014/96/2015-UR-NH-2 -dt.26.10.2016 Job No.NH-125-UR-2016-17-484
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
28208.00
Resanction Cost :
28208.00
Tentative Cost :
28208.00
Exp. Upto Last Fy :
53,360.63
For CFY 2024-2025
Remaining :
-25,152.63
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
53,360.63
Work completed
Sanction on : 8 years 1 month ago
26 Oct 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
15 Sep 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Old Chalthi Bridge Suspension bridle bridge at chalthi over ladhiya river