Work Profile Report [133W14]
Remarks
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : RO/UK/THDC/NH-09/2022-23/PKG-I
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
19222.48
Resanction Cost :
19222.48
Tentative Cost :
19222.48
Exp. Upto Last Fy :
1,218.03
For CFY 2024-2025
Remaining :
18,004.45
Demand :
8,000.00
Allotment :
5,242.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,218.03
Construction Started
Sanction on : 2 years 1 month ago
01 Nov 2022
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
74 %
Tentative Completion date on : 5 days 11 hours from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: khetkhola bridge amori