Work Profile Report [15W11]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 572/।।।-2/06- 8 (प्राआ0)/06 दिनांक 28-3-2006
TS Amount (lakhs) : 372.65 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
417.38
Resanction Cost :
417.38
Tentative Cost :
417.38
Exp. Upto Last Fy :
236.14
For CFY 2024-2025
Remaining :
181.24
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
236.14
Work completed
Sanction on : 18 years 11 months ago
28 Mar 2006
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 2 years 11 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
6किमी0 में पहाड कटान एंव पार्ट-।। का कार्य पूर्ण। -- as on 06-Dec-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Jamtari Baily Bridge
© PWD Uttarakhand