Work Profile Report [15W847]
Tenders
Project Activities
alerts
Administrative Approval Detail : शासन का पत्रांक संख्या-2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21 जुलाई, 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
231.99
Resanction Cost :
231.99
Tentative Cost :
231.99
Exp. Upto Last Fy :
180.52
For CFY 2024-2025
Remaining :
51.47
Demand :
51.47
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
180.52
Work completed
Sanction on : 1 year 4 months ago
21 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 6 months 5 days ago
18 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है । -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand