Work Profile Report [16W376]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 775/।।।(2)/16-11(प्रा0आ0)/2011 दिनांक 09.02.2016
TS Amount (lakhs) : 605.61 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
605.61
Resanction Cost :
605.61
Tentative Cost :
605.61
Exp. Upto Last Fy :
377.76
For CFY 2025-2026
Remaining :
227.85
Demand :
190.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
377.76
Construction Started
Sanction on : 9 years 2 months ago
09 Feb 2016
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
80 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.800 मी0 लम्बाई में पार्ट-।। एवं सम्पूर्ण लम्बाई में डिफेक्ट कटिंग का कार्य प्रगति पर। -- as on 02-Apr-2025
Assets :
© PWD Uttarakhand