Work Profile Report [16W569]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 4596/।।।(2)/21-45(एम0एल0ए0)/2017 टीसी0-। दिनांक 29 सितम्बर 2021
TS Amount (lakhs) : 87.87 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
87.87
Resanction Cost :
87.87
Tentative Cost :
85.09
Saving
2.78
Exp. Upto Last Fy :
76.48
For CFY 2024-2025
Remaining :
11.39
Demand :
5.00
Allotment :
1.54
Exp in CFY :
3.60
Total Up to Date Exp :
80.08
Work completed
Sanction on : 2 years 10 months ago
29 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 1 year 5 months ago
01 Mar 2023
Physical Linear Components
Remark
Overall Saving 2.78 has been recorded as expected cost of work reduced from 87.87 to 85.09 . -- as on 31-Jul-2024
Assets :
© PWD Uttarakhand