Work Profile Report [16W649]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी पिथौरागढ़ के पत्रांक 145/वा0जि0यो0/2021-22 दिनांक 17.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.00
Resanction Cost :
14.00
Tentative Cost :
14.00
Exp. Upto Last Fy :
7.00
For CFY 2024-2025
Remaining :
7.00
Demand :
6.35
Allotment :
6.35
Exp in CFY :
6.33
Total Up to Date Exp :
13.33
Construction Started
Sanction on : 1 year 6 months ago
17 May 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 16-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand