Work Profile Report [17W331]

बगडीहाट सावलीसेरा मोटर मार्ग में सुधारी करण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिलाधिकारी पिथौरागढ़ का पत्रांक 601/जि0यो0-प्र0वि0स्वी0/2022-23

TS Amount (lakhs) : 5.5 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

10.50

Resanction Cost :

10.50

Tentative Cost :

10.50

Exp. Upto Last Fy :

9.20

For CFY 2024-2025

Remaining :

1.30

Demand :

0.00

Allotment :

0.24

Exp in CFY :

0.24

Total Up to Date Exp :

9.44

Work completed

Sanction on : 2 years 5 months ago

27 Sep 2022

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 1 year 1 month ago

11 Jan 2024

Actual Completion Date : 1 year 4 months ago

18 Oct 2023

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य पूर्ण। -- as on 18-May-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Bagdihat