Work Profile Report [17W397]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0-फाईल संख्या 61108 लोक निर्माण अनुभाग-2 दिनांक 20-02-2024
TS Amount (lakhs) : 24.48 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.48
Resanction Cost :
24.48
Tentative Cost :
24.48
Exp. Upto Last Fy :
24.30
For CFY 2025-2026
Remaining :
0.18
Demand :
0.00
Allotment :
0.18
Exp in CFY :
0.00
Total Up to Date Exp :
24.30
Construction Started
Sanction on : 1 year 2 months ago
20 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 10 months 1 week ago
13 Jun 2024
Actual Completion Date : 9 months 1 day ago
25 Jul 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Oct-2024
© PWD Uttarakhand