Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16.5 | 16.5 | 16.5 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 | ||
Span of Bridges [m] | 21 | 43 | 43 | 0 |
19W13 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 764/।।। (2)/08-65 (प्राआ0)/2008, दिनांक 24-03-2008
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
671.73
Resanction Cost :
671.73
Tentative Cost :
671.73
Exp. Upto Last Fy : 2.48
For CFY 2024-2025
Remaining : 669.25
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.48
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Long Term Forest Approval
दिनांक 31-07-2021को वनभूमि प्रस्ताव आनलाईन किये गये थे, पुनः वन भूमि प्रस्ताव भारत सरकार से आपतियो में प्राप्त आपत्तियों के निराकरण के क्रम में CA LAND उपलब्ध कराने हेतु इस कार्यालय के पत्रांक 1292 /2 सी दिनांक 16.05 .2024 द्वारा जिला अधिकारी महोदय को पत्र प्रेषित किया गया है -- as on 04-Jul-2024
Physical Peramenters