Work Profile Report [19W13]

चम्पावत में बिनवाल गांव से कलियाधुरा मोटर मार्ग सेतुओं सहित।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 764/।।। (2)/08-65 (प्राआ0)/2008, दिनांक 24-03-2008

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

671.73

Resanction Cost :

671.73

Tentative Cost :

671.73

Exp. Upto Last Fy :

2.48

For CFY 2024-2025

Remaining :

669.25

Demand :

0.00

Allotment :

0.25

Exp in CFY :

0.25

Total Up to Date Exp :

2.73

Alignment Approved

Sanction on : 16 years 7 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 7 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
16.5
16.5
0.000
16.5
0.000
0.000
Bridge
3 (21m)
3 (43m)
0 (0.000m)
3 (43m)
0 (0.000m)
0 (0.000m)

Remark

view all

दिनांक 31-07-2021को वनभूमि प्रस्ताव आनलाईन किये गये थे, पुनः वन भूमि प्रस्ताव भारत सरकार से आपतियो में प्राप्त आपत्तियों के निराकरण के क्रम में CA LAND उपलब्ध कराने हेतु इस कार्यालय के पत्रांक 1292 /2 सी दिनांक 16.05 .2024 द्वारा जिला अधिकारी महोदय को पत्र प्रेषित किया गया है जिला अधिकारी महोदय द्वारा क्षतिपूरक ब्रक्षयरोपण हेतु भूमि उपलब्ध कराने के पश्चात आपत्तियों का निराकरण कर प्रस्ताव पुनः आॅनलाईन कर दिया गया है। वर्तमान में प्रस्ताव C.F. स्तर में है। -- as on 04-Oct-2024

Rating : 0

Forest Case Pending At : 06: Conservator

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand