Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16.5 | 16.5 | 16.5 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 | ||
Span of Bridges [m] | 21 | 43 | 43 | 0 |
19W13 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 764/।।। (2)/08-65 (प्राआ0)/2008, दिनांक 24-03-2008
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 671.73 Lacs
Resanction Cost : 671.73 Lacs
Exp. Upto Last Fy : 2.48 Lacs
For CFY 2024-2025
Remaining : 669.25 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.48 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 08: State Government
Bottelneck: Long Term Forest Approval
दिनांक 31-07-2021को वनभूमि प्रस्ताव आनलाईन किये गये थे, जो नोडल अधिकारी से आपत्ति में प्राप्त, आपत्तियों का निराकरण उपरान्त वर्तमान में वन भूमि प्रस्ताव राज्य सरकार स्तर पर । -- as on 28-Apr-2024
Physical Peramenters