Work Profile Report [19W652]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter no.-31110, date-27-07-2022
TS Amount (lakhs) : 1377.14 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1377.14
Resanction Cost :
1377.14
Tentative Cost :
1377.14
Exp. Upto Last Fy :
457.52
For CFY 2024-2025
Remaining :
919.62
Demand :
919.62
Allotment :
681.60
Exp in CFY :
681.60
Total Up to Date Exp :
1,139.12
Construction Started
Sanction on : 2 years 3 months ago
27 Jul 2022
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
90 %
Tentative Completion date on : 1 month 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सेतु के स्लैब कंक्रीट का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 03-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: