Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.75 | 7.75 | 0.000 | 7.75 | 7.750 | 0.000 |
19W690 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक-16-05-2023 द्वारा स्वीकृत।
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
177.06
Resanction Cost :
177.06
Tentative Cost :
177.06
Exp. Upto Last Fy : 14.47
For CFY 2024-2025
Remaining : 162.59
Demand : 162.59
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 14.47
Work completed
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 01-Jul-2024
Physical Peramenters