Work Profile Report [19W747]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1346.00
Resanction Cost :
1339.25
Tentative Cost :
1339.25
Exp. Upto Last Fy :
1,074.87
For CFY 2025-2026
Remaining :
264.38
Demand :
264.38
Allotment :
62.52
Exp in CFY :
62.52
Total Up to Date Exp :
1,137.39
Construction Started
Sanction on : 1 year 3 months ago
29 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
95 %
Tentative Completion date on : 5 days 20 hours from now
14 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
बी0सी0 का कार्य पूर्ण। नाली निर्माण का कार्य प्रगति पर। -- as on 06-Jun-2025