Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 30 | 30 | 0.000 | 30 | 12.000 | 0.000 |
19W747 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1346.00
Resanction Cost :
1339.25
Tentative Cost :
1339.25
Exp. Upto Last Fy : 42.17
For CFY 2024-2025
Remaining : 1,297.08
Demand : 1,000.00
Allotment : 0.00
Exp in CFY : 323.09
Total Up to Date Exp : 365.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 50 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
10 months 3 weeks from now
14 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्वीकृत लंबाई के सापेक्ष 8 किमी0 लम्बाई में स्कपर व दीवारों का कार्य पूर्ण एवं 17.50 किमी लम्बाई मे बीसी का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters