Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 15 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 18 | 18 | 18 | 0 |
1W10 :
Administrative Approval Detail : शा0सं0 2488/।।।- (2) /08-03(मु0मं0घो0) /08 दिनंाक 25 जुलाई, 2008
TS Amount (lakhs) : 525 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
525.00
Resanction Cost :
525.00
Tentative Cost :
525.00
Exp. Upto Last Fy : 511.04
For CFY 2024-2025
Remaining : 13.96
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 511.04
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य की स्वीकृत लम्बाई 15 कि0मी0 के सापेक्ष् उपलब्ध धनराशि के अन्तर्गत 15 कि0मी0 पहाड़ कटान का कार्य पूर्ण एवं 12 कि0मी0 लम्बाई में पार्ट-।। का कार्य पूर्ण हो चुका है। अवशेष कार्य हेतु पुनरीक्षित आगणन कार्यालय मुख्य अभियन्ता, लो0नि0वि0, अल्मोड़ा के पत्रांक 520/101याता0-अ0/2023 दिनंाक 27.04.2023 द्वारा स्वीकृति हेतु शासन को प्रेषित किया गया है। -- as on 06-Jul-2024
Physical Peramenters