Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
1W464 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Daulaghat Bridge
Administrative Approval Detail : श्शासनादेश संख्या 3183/।।।(2)-19-51(एम.एल.ए.)/2017 टी0सी0 दिनंाक 19 अगस्त, 2019
TS Amount (lakhs) : 318.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
318.83
Resanction Cost :
318.83
Tentative Cost :
318.83
Exp. Upto Last Fy : 251.07
For CFY 2024-2025
Remaining : 67.76
Demand : 5.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 251.07
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 10 months ago
19 Aug 2019
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
8 months 2 weeks ago
30 Oct 2023
Remark
Bottelneck: no issue
मार्ग में पड़ने वाले 24 मीटर स्पान सेतु के दाहिने अबटमेन्ट निर्माण हेतु कम गहराई में पक्की चट्टान मिल जाने से अबटमेन्ट कार्य में बचत हुई है तथा निविदा कम दरों में प्राप्त होने पर कार्य में बचत हुई है। माह 10/2023 में कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 18-Jan-2024
Physical Peramenters