Work Profile Report [1W567]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन का पत्राक 3602 /III (2)/48/((प्रा०आ०)/2018 dated14-09-2021
TS Amount (lakhs) : 334.03 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
334.03
Resanction Cost :
334.03
Tentative Cost :
334.03
Exp. Upto Last Fy :
311.57
For CFY 2025-2026
Remaining :
22.46
Demand :
0.00
Allotment :
3.45
Exp in CFY :
0.00
Total Up to Date Exp :
311.57
In Maintenance After Completion
Sanction on : 3 years 6 months ago
14 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 6 months ago
15 Sep 2023
Actual Completion Date : 1 year 5 months ago
31 Oct 2023
Physical Linear Components
Remark
निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 30-Jun-2023