Work Profile Report [1W584]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : GO letter no 2390/III(2)/21-52(MLA)/2017 TC दिनांक 04-08-2021
TS Amount (lakhs) : 166.26 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
166.26
Resanction Cost :
166.26
Tentative Cost :
166.26
Exp. Upto Last Fy :
106.69
For CFY 2024-2025
Remaining :
59.57
Demand :
30.00
Allotment :
30.00
Exp in CFY :
22.25
Total Up to Date Exp :
128.95
Construction Started
Sanction on : 3 years 1 week ago
04 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
75 %
Tentative Completion date on : 7 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दोनों अबेटमेंट का कार्य पूर्ण एवं इरेक्शन का कार्य भी पूर्ण। -- as on 11-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: