Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
1W591 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 38879 दिनंाक 31-03-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
313.08
Resanction Cost :
313.08
Tentative Cost :
313.08
Exp. Upto Last Fy : 83.13
For CFY 2024-2025
Remaining : 229.95
Demand : 187.00
Allotment : 120.00
Exp in CFY : 0.00
Total Up to Date Exp : 83.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 50 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
सोलिंग कोट, इन्टरकोट का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 03-Jul-2024
Physical Peramenters