Work Profile Report [1W592]

विधानसभा क्षेत्र सोमेश्वर में मजखाली-सुन्दरखाल-बिटुलिया मोटर मार्ग में डामरीकरण का कार्य (द्वितीय चरण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 51743 दिनंाक 28-03-2023

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

185.36

Resanction Cost :

185.36

Tentative Cost :

185.36

Exp. Upto Last Fy :

30.25

For CFY 2024-2025

Remaining :

155.11

Demand :

135.00

Allotment :

80.00

Exp in CFY :

145.21

Total Up to Date Exp :

175.46

Construction Started

Sanction on : 1 year 4 months ago

28 Mar 2023

Physical Progress:

At start of FY 2024-2025 :

30 %

Up to Date :

90 %

Tentative Completion date on : 7 months 1 week from now

30 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
3.000
0
3.000
0.000

Remark

view all

सोलिंग, इन्टर, टाॅपकोट का कार्य पूर्ण। पी0सी0 का कार्य 3.00 कि0मी0 के सापेक्ष 2.50 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 03-Jul-2024

Rating : 193

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: