Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 51743 दिनंाक 28-03-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
185.36
Resanction Cost :
185.36
Tentative Cost :
185.36
Exp. Upto Last Fy :
30.25
For CFY 2024-2025
Remaining :
155.11
Demand :
135.00
Allotment :
80.00
Exp in CFY :
145.21
Total Up to Date Exp :
175.46
Construction Started
Sanction on : 1 year 4 months ago
28 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
90 %
Tentative Completion date on : 7 months 1 week from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग, इन्टर, टाॅपकोट का कार्य पूर्ण। पी0सी0 का कार्य 3.00 कि0मी0 के सापेक्ष 2.50 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 03-Jul-2024