Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
1W81 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 827/।।।-2/06-76 (प्रा0आ0)/05 दिनांक 28.03.06
TS Amount (lakhs) : 0.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.20
Resanction Cost :
71.20
Tentative Cost :
71.20
Exp. Upto Last Fy : 2.32
For CFY 2024-2025
Remaining : 68.88
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.32
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
18 years 3 months ago
28 Mar 2006
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: Long Term Forest Approval
भारत सरकार द्वारा वैकल्पिक संरेखण का परीक्षण किये जाने हेतु दिनाॅक 28.04.2023 को प्रस्ताव आपत्तियों में प्राप्त। आपत्तियों के निराकरण हेतु इस कार्यालय के पत्र सं0 761/7सी0 दिनंाक 02.05.2023 द्वारा 1.966 है0 क्षतिपूरक वृक्षारोपण हेतु भूमि की मांग प्रभागीय वनाधिकारी अल्मोड़ा वन प्रभाग अल्मोड़ा से की गयी है। -- as on 10-Nov-2023
Physical Peramenters