Work Profile Report [1W84]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 830/।।।(2)/ 08-29(प्रा0आ0)/07 दिनांक 24.03.2008
TS Amount (lakhs) : 98.54 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
117.00
Resanction Cost :
117.00
Tentative Cost :
117.00
Exp. Upto Last Fy :
55.00
For CFY 2024-2025
Remaining :
62.00
Demand :
15.00
Allotment :
15.00
Exp in CFY :
8.54
Total Up to Date Exp :
63.53
Construction Started
Sanction on : 16 years 9 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
40 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान एवं पार्ट-।। का कार्य 1.75 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 16-Dec-2023
Assets :
© PWD Uttarakhand