Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 0 | 0 |
Closed Work 23W1056 :
Administrative Approval Detail : शा0 सं0- 1693/ााा(2)/21-67(एम0एल0ए0)/2017 टी0सी0 ा दिनांक-16 जून, 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.86
Resanction Cost :
27.86
Tentative Cost :
27.86
Exp. Upto Last Fy : 13.04
For CFY 2024-2025
Remaining : 14.82
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.04
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
16 Jun 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
2 years 2 months ago
01 May 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Dec-2022
Physical Peramenters