Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17.7 | 17.7 | 17.7 | 0 |
Closed Work 23W1122 :
Administrative Approval Detail : G.O. no.- 1170/ III(3)/2021-07 (C.R.I.F.)/2021
TS Amount (lakhs) : 5373.67 Lacs
Financial Detail
Sanction Cost : 5,373.67 Lacs
Resanction Cost : 5,373.67 Lacs
Exp. Upto Last Fy : 5,373.66 Lacs
For CFY 2024-2025
Remaining : 0.01 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5,373.66 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
27 Oct 2021
Tentative Completion date:
11 months 5 hours ago
31 Jul 2023
Actual Completion Date:
8 months 4 weeks ago
03 Oct 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-Nov-2023
Physical Peramenters