Work Profile Report [24W772]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 1364/।।।(2) /20-70 (एम0एल0ए0) /2017 टी0सी0 - ।।। दिनांक 20-05-2021
TS Amount (lakhs) : 110.93 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
110.93
Resanction Cost :
110.93
Tentative Cost :
110.93
Exp. Upto Last Fy :
102.69
For CFY 2024-2025
Remaining :
8.24
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
102.69
Construction Started
Sanction on : 3 years 7 months ago
20 May 2021
Physical Progress:
At start of FY 2024-2025 :
1 %
Up to Date :
95 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 पूर्ण। पटरी प्रगति में। -- as on 01-Sep-2022
Assets :