Work Profile Report [24W839]
Fin Plan
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : GO No- 6173/III(2)/21-70(MLA)/2017 TC 5 Date 22-12-2021
TS Amount (lakhs) : 999.75 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
999.75
Resanction Cost :
999.75
Tentative Cost :
999.75
Exp. Upto Last Fy :
981.00
For CFY 2024-2025
Remaining :
18.75
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
981.00
Work completed
Sanction on : 2 years 11 months ago
22 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 5 months ago
15 Jun 2022
Actual Completion Date : 2 years 3 months ago
06 Aug 2022
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 01-Sep-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: unknown bridge Jhankaiya Arc Bridge at Khatima Melaghat