Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.3 | 24.3 | 24.3 | 0 |
Closed Work 24W839 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: unknown bridge Jhankaiya Arc Bridge at Khatima Melaghat
Administrative Approval Detail : GO No- 6173/III(2)/21-70(MLA)/2017 TC 5 Date 22-12-2021
TS Amount (lakhs) : 999.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
999.75
Resanction Cost :
999.75
Tentative Cost :
999.75
Exp. Upto Last Fy : 981.00
For CFY 2024-2025
Remaining : 18.75
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 981.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
22 Dec 2021
Tentative Completion date:
2 years 1 month ago
15 Jun 2022
Actual Completion Date:
1 year 11 months ago
06 Aug 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Sep-2022