Work Profile Report [24W856]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO No- 443/III(2)/21-70(MLA)/2017 TC -4 Date 07-01-2022
TS Amount (lakhs) : 88.82 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.82
Resanction Cost :
88.82
Tentative Cost :
88.82
Exp. Upto Last Fy :
88.26
For CFY 2024-2025
Remaining :
0.56
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
88.26
Construction Started
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 3 months ago
31 Aug 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। मौसम अनुकूल होने पर कार्य प्रारम्भ किया जायेगा। -- as on 01-Sep-2022
Assets :