Work Profile Report [24W981]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0पत्रावली संख्या 56385/।।।(2)/2024-1(प्रा0आ0)/2023 दिनांक 16.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
489.68
Resanction Cost :
489.68
Tentative Cost :
489.68
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
489.68
Demand :
489.68
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 8 months 1 week ago
16 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 4 months 6 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। साइट क्लीयरेंस का कार्य प्रगति में। -- as on 23-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand