Work Profile Report [25W1042]
Fin Plan
Tenders
Project Activities
Documents
Administrative Approval Detail : शा0सं0 303/।।।(2)/19 -65(एम0एल0ए0)/ 2017 टी0सी0 दिनांक 20.1.2020
TS Amount (lakhs) : 318.82 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
318.82
Resanction Cost :
318.82
Tentative Cost :
307.96
Saving
10.86
Exp. Upto Last Fy :
307.96
For CFY 2024-2025
Remaining :
10.86
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
307.96
In Maintenance After Completion
Sanction on : 4 years 6 months ago
20 Jan 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 months ago
04 Apr 2022
Actual Completion Date : 2 years 4 months ago
04 Apr 2022
Physical Linear Components
Remark
Overall Saving 10.86 has been recorded as expected cost of work reduced from 318.82 to 307.96 . -- as on 29-Jul-2024