Work Profile Report [25W1064]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1428(।)/।।।(2)/21-62(एम0एल0ए0)/2017 दिनांक 2.6.2021
TS Amount (lakhs) : 81.23 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.23
Resanction Cost :
81.23
Tentative Cost :
81.23
Exp. Upto Last Fy :
76.84
For CFY 2024-2025
Remaining :
4.39
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
76.84
Construction Started
Sanction on : 3 years 5 months ago
02 Jun 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
65 %
Tentative Completion date on : 1 year 8 months ago
15 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.50 किमी0 में डब्लू0एम0एम0 का कार्य पूर्ण शेष प्रगति पर। -- as on 14-Nov-2022