Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.628 | 24.628 | 24.628 | 0 |
Closed Work 25W1083 :
Administrative Approval Detail : एन0एच0ए0आई0 परियोजना इकाइ नजीबाबाद का पत्रांक NHAI /PIU-NBD/NH-74/44053 /R&M/2016 /10010 dt 23-6-2021 and NHAI/PIU-NBD/NH-74/ 44053 /R&M /2016 /9931 dt 12-6-2021
TS Amount (lakhs) : 1647 Lacs
Financial Detail
Sanction Cost : 1,647.00 Lacs
Resanction Cost : 1,647.00 Lacs
Exp. Upto Last Fy : 1,791.21 Lacs
For CFY 2024-2025
Remaining : -144.21 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 24.92 Lacs
Total Up to Date Exp : 1,816.13 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 1 week ago
23 Jun 2021
Tentative Completion date:
1 year 9 months ago
30 Sep 2022
Actual Completion Date:
4 months 2 weeks ago
15 Feb 2024
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 11-Apr-2024
Physical Peramenters