Work Profile Report [25W1089]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3228 /।।। (2)/21 -64 (एम0एल0ए0) /2017 टी0सी0-। दिनांक 28.8.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.48
Resanction Cost :
54.48
Tentative Cost :
54.48
Exp. Upto Last Fy :
49.42
For CFY 2025-2026
Remaining :
5.06
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
49.42
Construction Started
Sanction on : 3 years 7 months ago
28 Aug 2021
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 weeks ago
15 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 21-Nov-2022
Assets :