Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.38 | 2.38 | 2.38 | 0 |
Closed Work 25W1098 :
Administrative Approval Detail : शा0सं0 4040 /।।। (2)/ 21- 65 (एम0एल0ए0) /2017 टी0सी0।।। दि0 20.9.21
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
106.21
Resanction Cost :
106.21
Tentative Cost :
106.21
Exp. Upto Last Fy : 79.69
For CFY 2024-2025
Remaining : 26.52
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 79.69
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
20 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 21-Jun-2022
Physical Peramenters