Work Profile Report [25W1111]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /110015 /2023 (ई0 फाईल सं0 28686) दि0 25.3.23
TS Amount (lakhs) : 553.25 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
553.25
Resanction Cost :
553.25
Tentative Cost :
447.25
Saving
106.00
Exp. Upto Last Fy :
446.96
For CFY 2025-2026
Remaining :
106.29
Demand :
0.00
Allotment :
254.73
Exp in CFY :
0.00
Total Up to Date Exp :
446.96
Work completed
Sanction on : 2 years 2 weeks ago
25 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
100 %
Tentative Completion date on : 9 months 1 week ago
03 Jul 2024
Actual Completion Date : 9 months 1 week ago
30 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण -- as on 30-Mar-2025
Assets :