Work Profile Report [25W1175]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /183608 /2024 (ई0 फाईल सं0 50220) दि0 22.01.2024
TS Amount (lakhs) : 144.75 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
144.75
Resanction Cost :
144.75
Tentative Cost :
141.50
Saving
3.25
Exp. Upto Last Fy :
141.27
For CFY 2025-2026
Remaining :
3.48
Demand :
0.00
Allotment :
87.59
Exp in CFY :
0.00
Total Up to Date Exp :
141.27
In Maintenance After Completion
Sanction on : 1 year 2 months ago
22 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 2 days ago
10 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण अनुरक्षण कार्य शेष। -- as on 30-Mar-2025
Assets :