Work Profile Report [25W1176]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 ।/189377/2024 (ई0 फाईल सं0- 68208) दि0 09.02.2024
TS Amount (lakhs) : 121.62 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.62
Resanction Cost :
121.62
Tentative Cost :
75.00
Saving
46.62
Exp. Upto Last Fy :
10.27
For CFY 2024-2025
Remaining :
111.35
Demand :
60.00
Allotment :
30.00
Exp in CFY :
23.78
Total Up to Date Exp :
34.05
Construction Started
Sanction on : 6 months 1 week ago
09 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
40 %
Tentative Completion date on : 3 months 2 weeks from now
01 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 46.62 has been recorded as expected cost of work reduced from 121.62 to 75 . -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand