Work Profile Report [25W1176]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/189377/2024 (ई0 फाईल सं0- 68208) दि0 09.02.2024
TS Amount (lakhs) : 121.62 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
121.62
Resanction Cost :
121.62
Tentative Cost :
75.00
Saving
46.62
Exp. Upto Last Fy :
10.27
For CFY 2024-2025
Remaining :
111.35
Demand :
60.00
Allotment :
46.94
Exp in CFY :
24.16
Total Up to Date Exp :
34.43
Construction Started
Sanction on : 9 months 2 weeks ago
09 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
40 %
Tentative Completion date on : 3 months 1 week from now
01 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्लम द्वारा मार्ग का सुरक्षात्मक कार्य पूर्ण, शेष कार्य प्रगति में -- as on 24-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: