Work Profile Report [30W1242]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 104/रा0यो0आ0/जि0यो0/2020-21 दि0 05-11-20
TS Amount (lakhs) : 30 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.44
Resanction Cost :
89.44
Tentative Cost :
89.44
Exp. Upto Last Fy :
78.65
For CFY 2025-2026
Remaining :
10.79
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
78.65
Construction Started
Sanction on : 4 years 5 months ago
05 Nov 2020
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 1 year 5 months ago
31 Oct 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 04-May-2024
Assets :