Work Profile Report [30W1311]

Closed Work fवत्तीय वर्ष 2021-22 मे नवीनीकरण के अन्तर्गत बन्दरकोट-बौन मोटर मार्ग के fकमी0 1, 3 एवं 5 मे पी0सी0 द्वारा नवीनीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : HOD latter 363/14 yata (k) /pra -U /2020 dt 23-03-2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

38.52

Resanction Cost :

38.52

Tentative Cost :

38.52

Exp. Upto Last Fy :

38.52

For CFY 2024-2025

Remaining :

0.00

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

38.52

Work completed

Sanction on : 3 years 8 months ago

23 Mar 2021

Physical Progress:

At start of FY 2024-2025 :

1 %

Up to Date :

0 %

Tentative Completion date on : 2 years 7 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
3
-

Remark

view all

work completed -- as on 03-Apr-2022

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand