Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
30W254 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Kandola suspension bridge Kedarghat suspension bridge
Administrative Approval Detail : 5384/।।।:2ः/10-02:एम0एल0ए0ः/10 दि0 13-12-10
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 12.60 Lacs
Resanction Cost : 12.60 Lacs
Exp. Upto Last Fy : 1.56 Lacs
For CFY 2024-2025
Remaining : 11.04 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.56 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
13 years 6 months ago
13 Dec 2010
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
शा0सं0- 2307/।।।(2)/16-03 (एम0एल0ए0)/2015 दिनांक 11-08-16 द्वारा द्वितीय चरण की स्वीकृति रू0 273.60 लाख की स्वीकृति प्राप्त। वनभूमि की सैद्धान्तिक स्वीकृति प्राप्त कर ली गयी है। अपर प्रमुख वन संरक्षक एवं नोडल अधिकारी वन संरक्षण देहरादून के पत्रांक-1566/FP/UK/ROAD/18704/2016 दिनांक 29.12.2021 के द्वारा उल्लिखित बिन्दुओं का अनुपालन कर सूचना मूल प्रति सहित अवगत कराने हेतु लिखा गया एवं कार्यालय अधिशासी अभियन्ता प्रान्तीय खण्ड, लो0नि0वि0 उत्तरकाशी के पत्रांक-338/वनभूमि दिनांक 16.02.2023 को प्रभागीय वनाधिकारी को पत्र लिखा गया एवं अनुपालन आख्या आॅन लाईन अपलोड कर दी गयी, जो नोडल स्तर पर लम्बित है। द्वितीय चरण का कार्य पूर्ण। -- as on 30-Dec-2023
Physical Peramenters