Work Profile Report [31W409]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : -शा0 सं0-535/।।। 2 /16-03 एम0एल0ए0/2015 दिनांक 29 फरवरी 2016
TS Amount (lakhs) : 149.75 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
149.75
Resanction Cost :
149.75
Tentative Cost :
149.75
Exp. Upto Last Fy :
95.73
For CFY 2024-2025
Remaining :
54.02
Demand :
30.00
Allotment :
0.00
Exp in CFY :
20.81
Total Up to Date Exp :
116.54
Work completed
Sanction on : 8 years 8 months ago
29 Feb 2016
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 6 days 5 hours from now
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: