Work Profile Report [32W1249]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन का शासनादेश संख्या 2451/।।। (2)/23-01 (प्रा.आ.)/2019, दिनांक 21.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.56
Resanction Cost :
140.56
Tentative Cost :
140.56
Exp. Upto Last Fy :
140.28
For CFY 2025-2026
Remaining :
0.28
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
140.28
Work completed
Sanction on : 1 year 9 months ago
21 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 day ago
25 Mar 2025
Actual Completion Date : 1 month 1 day ago
25 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: pujargaon-bangaon pul khalati tok puliya