Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 |
34W861 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2396/।।।(2)/18-26(प्रा0आ0) /2017 दिनांक 30.5.2018
TS Amount (lakhs) : 45.69 Lacs
Financial Detail
Sanction Cost : 45.69 Lacs
Resanction Cost : 45.69 Lacs
Exp. Upto Last Fy : 2.30 Lacs
For CFY 2024-2025
Remaining : 43.39 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.30 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
5 years 11 months ago
30 May 2018
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
संमरेखण अनुमादित। वनभूमि प्रस्ताव आॅन लाईन गठित। -- as on 14-Apr-2023
Physical Peramenters