Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 10.175 | 10.175 | 0 |
36W232 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 4886/।।।(2)/15-10(मु॰मं॰घो॰)/2015 दिनांक 22.07.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.40
Resanction Cost :
94.40
Tentative Cost :
94.40
Exp. Upto Last Fy : 0.53
For CFY 2024-2025
Remaining : 93.87
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.53
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 11 months ago
22 Jul 2015
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: CA Land
क्षतिपूरक वृक्षारोपण हेतु चयनित भूमि का संयुक्त निरीक्षण दिनांक 07.06.2024 को पूर्ण, आख्या अपेक्षित। -- as on 01-Jul-2024
Physical Peramenters