Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
36W435 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य विकास अधिकारी,चमोली के पत्रांक 225/जि॰यो॰/2023-24 दिनांक 01 जून 2023 द्वारा
TS Amount (lakhs) : 10.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.50
Resanction Cost :
10.50
Tentative Cost :
10.50
Exp. Upto Last Fy : 7.00
For CFY 2024-2025
Remaining : 3.50
Demand : 3.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
01 Jun 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 29-Feb-2024
Physical Peramenters